NSW government dropped a bomb on us, Sydney light rail contractor says

Acciona Australia tells parliamentary inquiry state government did not provide key information about power utilities

The Spanish contractor tasked with building Sydney’s delayed light rail says it would never have agreed to undertake the project if it had been given access to what one senior manager described as a terrifying document.

Acciona Australia’s managing director, Bede Noonan, on Thursday told a New South Wales parliamentary inquiry into the beleaguered project that the government had not provided key information about power utilities.

Continue reading...